Saturday, July 2, 2016

What Makes Your Product Valuable? Journey on the Value Stream - Part 3 on Organizational Improvement

In our previous discussions I introduced concepts around how to start organizational change from a 
combined bottom up/top down approach. We have discussed how to introduce an initiative which focuses on improving the organization in terms of value delivery.  We have also discussed how to mind map the organization to find troubles, constraints and a true picture of your company.  Once your problems have been identified it can be easy to try to simply "fix" the problem.  What I mean is that human tendency is to correct what we think is the biggest perceived symptom.  Approaches of this nature commonly lacks greater vision and likely only moves the problems or defers to another bottleneck.  When this shortsighted plan just defers to the next constraint the whole effort  is often construed as a failure.  What must be considered when facing organizational change is the value stream as a whole. Understand as many constraints or non-value added activities as possible when mapping the stream.  In all my consulting experience I have never seen an organization who begins a value stream map exceeding 6% of value added activity.  Setting expectations with leaders from the start to have patience is a key to organizational improvement. 

I was working with a development team who believed they needed to hire more developers because it was taking six months to get code released (forget agile for the moment)to production.  This was their problem statement (and their perceived solution).  After creating a value stream map of the development cycle we learned that the cycle time was almost 900 working hours.  Four hours of that time was spent developing.  Roughly 80% of that time was wait time.  Had the team hired more developers they could have attempted to double their productivity and take two hours out of their total cycle time.  Wow what an expensive solution.  Or they could have eliminated several management meetings which were simply rubber stamp approvals to move forward.  Reducing the meetings took 300 hours off of the total cycle time, and it cost nothing to implement.  To get that efficiency gain by hiring developers is simply impossible yet this is most commonly the first solution to reduce development value stream times. 

The concept of value stream mapping has been written very extensively and while there are many good posts most simply introduce the concept but fail at plugging the concept in to something actionable. Or they prescribe perfect ways to change your value stream without providing a lesson on why focusing on the value stream is relevant. I will refer to many smarter practitioners through this blog but it's important to define what value stream mapping can accomplish in terms of starting organizational change.  The LSS Academy has put it best at defining a value stream as "A value stream can be defined as all the steps – both value added and non value added – required to take a product or service from its raw materials state into the waiting arms of a happy customer."  Again the concept of value in this scenario is simply what your customer is willing to pay for.  We know that there are Value Added (VA) activities which the customer finds worth to pay for.  Non-Value Added (NVA) activities are usually where great debate begins.  This work is often very overwhelming and it's not a bad idea to look for an outside consultant to help you.  This is really the only time where I encourage going outside to make this success. 

Again it's important to remember why we are doing all these activities. Shigeo Shingo said, “The four goals of improvement must be to make things easier, better, faster, and cheaper.”  Note the sequence of this list; Lean focuses on adding value and eliminating waste through simplification, quality improvement, and lead time reduction; cost reduction is a natural outcome. According to Gartner, “One of the biggest mistakes companies make with Lean is focusing too heavily on driving cost out of the business. If you approach Lean with that attitude, you’re bound to fail. Building a huge data center may give you great economies of scale, for example, but it may also reduce agility and flexibility.”(Bell, Steven C. (2012-01-04). Lean IT: Enabling and Sustaining Your Lean Transformation)

Consider your own organization, you are likely structured in the form of departments which scale and report vertically. Who is responsible for the product from inception to cash?  A value stream is the horizontal flow of your product from that inception to cash.  This will feel odd to your organization because they rarely care about their products in that manner. 

The best analogy is to compare the value stream to a story.  A product begins its journey in marketing and end in accounts payable.  The key to creating an excellent current state VSM is to document what you actually see with your own eyes. We are not interested in how the process is supposed to work, or was designed to work.  Instead, we are interested in how the process is performing today. Will the process change a bit tomorrow? Sure. But that’s OK. In fact it's encouraged.   There a many different ways to create a value stream map and my personal opinion is that you use one that works for you.  As long as the result of the exercise is to identify your waste or NVA activities in your stream.  Below is a good example I found from ASQ on a simple value stream map.  

Now lets get started.  The teams created for the prior steps in this journey should also be used to value stream map.  They will understand the mapping and problems in the organization best and it's encouraged you stick with those team members.  They are likely the only people who have ever looked at the organization horizontally versus vertically.  For example I once worked with a large insurance organization who were structured in to operating companies.  No big surprise there but each OP Co. was designed to support certain business segments (home insurance, life insurance, investments).  Within each segment we also saw turf wars where they hesitated in helping other departments.  Activities as easy as sharing customer information or transferring phone calls from the customer were almost impossible to accomplish.   Where's the value in this line of thinking?  Well it's easy to keep that mind set when you only look within you own department.  Encourage your people to think across the value stream and you will see very different outcomes. 

1. Draw the current state value stream map with all of the steps, delays, and information flows required to deliver the target service. IF you're interested in some templates please contact me. 

2. Assess the current state value stream map in terms of flow and waste. Collect all missing data (e.g., value added, cycle time, etc.).
3. Calculate the total lead time and value added time.4. Identify and list all areas of waste (e.g., inventory, transportation, etc.).
5. Develop a list of opportunities for improvement based on these observations.

Below is a great example of mind mapping a development process (From the blog Wide Awake Developers, This can show a good example of how Agile and Lean can fit together in the IT world.  Think of an agile activity as something which could exists more at an execution level in each activity while the Lean Value Stream focuses on the end to end process. 

I’m going to use the prescribed method from the LSS Academy below.  Now this has a manufacturing focus but can easily be replaced with services or code.

Walk the process front to back. Quickly walk the process with your team in order to understand the general flow. It’s important to also define the start and stop point of the process. Don’t attempt to take on too much. Remember, we eat an elephant one bite at a time.

Draw in the customer box / details. In the top right hand side of the paper we draw the little saw topped box representing our customer.
We also note their monthly and/or daily demand along with the takt time as calculated in step

Go to the end! Next, we start at the END of the process and begin drawing the map back to front. And don’t forget about that eraser. You will need it. Nominiate a scribe and have them draw the map for the team.
Another trick is to ask each person on the team to map it out so you can compare and consolidate when you get back to the room. Yet another trick is to have the team divide and conquer as you send some off to map the beginning section, some to the middle, and some to the end.  There are many ways to do this. Experiment and do what works best for your situation.

Focus on the flow first. Focus on the flow side of things first (bottom portion of the map). This includes the process boxes and data boxes.  Regarding the data boxes, if you don’t have all the data perfectly collected on the day of the mapping exercise just do the best you can. You can always assign homework to go back and validate the figures later. In fact, even if you think you have solid data, the six sigma side of me urges you to validate your measurement systems to make sure we can trust the data. If you want to get really tricky state both a measure of central tendency and dispersion. You won’t see this advice in most lean VSM books… I guarantee it!
After studying the KB&R manufacturing process for an afternoon we learned that each process step is staffed with 1 operator. We also collected cycle time information at each step. Additional “homework” will be to collect information such as defect rates and changeover times.

Add the Inventory/Wait Times. Once you have all the process and data boxes in, it’s time to add in inventory and/or waiting times.   For inventory, we simply count the number of components in between the processes and note them under the triangle.

We also want to convert these components into days’ supply. To do this, we divide the number of components by the average daily demand (which we used to calculate takt time).
So, if your average daily demand is 10 components and you count 20 components of inventory in between process step A and process step B you have 2 days’ supply (20/10) in between the two processes. We will note this number on our timeline (to be added in a future step).
Lastly, don’t attempt to map every part number! Choose one or two key components to start with. You can always add more to the map later. In our example, we chose to simply count two components of bread as one subassembly since they move together down the production line.
Also, we are not accounting for the peanut butter and jelly “raw material” at this point since KB&R’s expert supply chain team negotiated a killer consignment stock deal with Sam’s Club so this inventory is quite low on the line. During the study, we learned that, as one example, there were 486 sub-assemblies (972 components of bread) in between the jelly application and packaging stations. This equates to 0.69 days’ supply (486 units / 700 daily demand).

Lastly, during the walk through of the process we noticed that each process step seemed to be working in isolation. In other words, the lady working at the peanut butter application seemed to produce as many units as she could and then pushed them along to the jelly application process.
This “push” process is found in just about every mass production process known to mankind. When we see this pushing action we note it on a VSM with a dashed line through the yellow inventory symbol.

Draw in the information flow. This step is what really separates a VSM from traditional process maps in my opinion. You see, in addition to learning about how material flows we also want to understand how information flows.

For example, we want to know it is moves about electronically? If so, we use a lightning bolt looking arrowed line. Is it communicated manually? If so, we use a straight arrowed line.
During this step we also draw in our production control box. For many, this box will include the letters “MRP” in it. In most mass production systems we typically see several manual information (straight) lines coming out of the MRP box aimed straight at each process step box.
In our example, we learned that production schedules each process step in isolation. In other words, each work station gets its unique production schedule. We draw this using straight “manual” information lines.
We also add in the information flow from our customers as well as to our suppliers. In our example, we learned that PB&J’s customer sends 30 days electronic forecasts as well as electronic daily orders. Conversely, PB&J sends its bread supplier an electronic weekly forecast.

Add in the timeline. We can now add the timeline to the bottom of the value stream map. This saw tooth looking line helps us separate the value added cycle time (taken from data boxes) from the non-value added time (days’ or hours’ supply info).
The last step in the process is to sum up all the “value-add” cycle times and note them at the end of the timeline. Likewise, we also sum up the “inventory” times and note that on the timeline.

Points to keep in mind. 

Prepare for the High Cost of ParticipationWhile value steam mapping can be an effective process improvement tool, the cost to use it can be high. Like racing a top fuel dragster, value steam mapping requires the presence of highly skilled support team members who practice frequently. Because of the need for considerable detail, team members will spend hours, even days, to develop a comprehensive value steam map.
Unlike drag racing, where direct costs can be measured, value stream mapping involves the risk of opportunity costs that are difficult to quantify. Simpler, more productive tools that are easier to learn might be available to make describing the current process faster and more effective. Many organizations forget to consider these opportunity costs for using value stream mapping.

This take times.  Remember if you looking for a quick fix you might find it here but will quickly be disappointed when the entire effort fails.  This is not only a change to your process but more importantly it’s a change to your culture.  People take time to change.  If your leaders aren’t supporting this from the top down and in the long run then you’re just going to spin your wheels.
Other Problems will appear.  If you’re familiar with the Theory of Constraints then you know that anytime one bottleneck is identified and eliminated another one will appear.  That bottleneck as always been there but has not been your primary constraint.  Don’t be discouraged if you find a mind field of bottlenecks.  It’s proof that what you’re doing is working.

Thursday, June 9, 2016

Enterprise Wide Problem Mapping: Step 2 in Enterprise Transformation

This post is focused on identifying and prioritizing constraints within an organization as part of the transformation process.  It's important as leaders and knowledge workers that you take the problem solving (or as some call it Root Cause) step very seriously and more importantly patiently.  After all problem solving is usually the original intent for the majority of transformation efforts.  Womack describes four essential Lean management states of mind that must be cultivated for an authentic transformation with problem solving being a large component:
1. The Lean manager eagerly embraces the role of problem solver.
2. The Lean manager realizes that no manager at a higher level can or should solve a problem at a lower level—problems can only be solved where they live, by those living with them.
3. The Lean manager believes that all problem solving is about experimentation by means of Plan-Do-Check-Act.
4. The Lean manager knows that no problem is ever solved forever.
James Womack, “The mind of the Lean manager,” Lean Enterprise Institute Electronic Newsletter, July 30, 2009.

My first blog post was a summary of the steps which need to be taken in order to start an enterprise transformation by briefly discussing the management components which much be in place for any transformation to begin.  This second blog post was written to introduce the idea of thinking about organizations horizontally (value stream).  The first steps in an enterprise transformation are slow but are very important.  What is often overlooked is most organizations simply don't grasp how much help the average manager needs in learning to see the value stream or how eagerly managers  embrace the mind map once they see them. Now if only every manager and every mapping team can achieve and sustain the effort to understand current state.

Without a mind map (or other identifier) of the current state picture defined, your problem identification and consequent solutions will be hard to socialize.  Furthermore this activity is likely the first time you or your leaders will have seen your organization in this light. It will be  shocking with how large and thorough this map will be, especially considering this isn't an "organizational map".

All this work has not yet provided anything which traditional change programs would be considered a "win".  That's just the point, this is not a program.  This is a cultural transformation which will take time  between when this starts to when you will start to measure improvement.  It's important at this point to be patient as this phase in the process sees the problems and must have restraint to not try to solve them as they are identified. Be patient, you will get there.

The mind map is complete, now what?  Edward Deming said it right when he said most problems are because of process not people.  As a result it's important not to assess blame in these exercises.  There is little value in blaming others for the problems as it creates an atmosphere which does not facilitate positive results.  It's a good idea at this point to continue involving members of the team who created the mind map(s).  No manager at a higher level can or should solve a problem at a lower level. (And one of the worst abuses of lean tools lies in trying to do just this.) Instead, the higher-level manager can assign responsibility to a manager at a lower level to tackle the problem through a continuing dialogue, both vertically with the higher-level manager and horizontally with everyone actually touching the process causing the problem. Womack's lean law of organizational life is that problems can only be solved where they live, in conversation with the people who live with them and whose current actions are contributing to the problem. But this requires support, encouragement, and, yes, relentless pressure from the higher-level manager.

This point is where different methodologies and frameworks will diverge as well.  There is no right or wrong way to move forward from here.  The many variables of your situation as well as what type of organization you are will dictate the most sensible path.  You can use many different methods to determine the size of a problem as well.  The suggestion I will give is simply one path of many that can be successful.  Once a problem map has been identified you can easily insert it to the method which you find best suits your company (Theory of Constraints, BPR, TPM, Lean, Six Sigma, Agile, ETC).

Create a mind map of your issues.  What I mean by that is take the original mind map and create a correlating issues map.  Don't stop with the first few problems you encounter.  Try to make it as thorough as the mind map.  This is the map where you will look at activities to improve and/or ignore. We know it's not possible to fix everything now, but with this list you will be able to quickly take issues off the map when they are resolved as well as (and this important to do) add items when they appear.  Below is an example of a problem map I facilitated with a Quality Assurance (QA) group in a software development department.  You will note there are no solutions or assignment of blame.  Simply a map of what the problems are.

Again this map will likely be a first for your company.  It's not often a company has a map of their largest issues/complaints.  With this map you are now prepared to take a step which can start to deliver measurable results.  It's best to have your team who created this map sit on this for a couple days.  Have them think over what they have come up with.  Then get the group back together to discuss the problems and narrow down where to start.
Take the complete map and start talking about what are the biggest issues.  It's likely that the room will already have a consensus on the largest issues.  When there is a consensus on what the largest problem is.  Use what is known as the "5 Whys".  The 5 whys is a proven method to determine how to get to the root cause of a problem.  Rather then explain it myself I will borrow from a great book titled "Lean IT" by Steve Bell.

"The Five Whys is the simple method of asking, “Why?” repeatedly until the root cause of a problem is uncovered. Normally the root cause is reached by the time we ask the fifth why. When the team believes it has identified a root cause, it works backward using “Therefore…” to test its logic and ensure it hasn’t missed a step in the sequence. For example, if the team investigating IT service request delays would have used the Five Whys, it might have gone as follows: Had the team performed root cause analysis, it may have discovered that there was a need for improving underlying business processes and developing standard work before considering technology-based solutions (a common theme throughout this book)."

Bell, Steven C. (2012-01-04). Lean IT: Enabling and Sustaining Your Lean Transformation (Kindle Locations 4004-4010). Taylor & Francis.

Once you have found what you consider to be the largest problem in the mind map and the problem if fully agreed we will now take that issue and make it our first actionable item which we will focus on for our enterprise transformation.  That will be the topic of my next blog post - Value Stream Mapping.

Please let me know if you have any questions.  This topic is very broad and I am the first to admit there are many ways to achieve what I've explained .